PAC report to be assessed
Tynwald members will have two months to pick over a report which criticises the Department of Infrastructure's handling of the dredging of Peel harbour.
The Public Accounts Committee concluded the DoI circumvented a number of financial regulations, by sub-dividing parts of the contract so it didn't have to go to Treasury for approval.
The PAC's report will be laid before the court this month, but won't be debated until March.
Its chairman is Michael MHK Alf Cannan: