Project now expected to cost £70million to complete
The infrastructure minister says he's concerned the Isle of Man could be seen as a 'soft touch' after the cost of a new ferry terminal 'spiralled' out of control.
Tim Crookall will go back to Tynwald next week to ask for an additional £32 million in order to bring the Liverpool build to completion.
The now £70 million project has been referred for review as part of the political scrutiny procedure:
Tim Crookall says questions need to be asked about what went wrong:
Funding of government services 'not sustainable'
Manx Care undertaking 'comprehensive validation' of ENT waiting lists
Taxi fares on the Island to rise
Surgeon announces he's standing in General Election