Project was initially due to be completed by 28 October
Work on completing the Millennium Bridge flap gate project will continue for a further month.
The Department of Infrastructure has confirmed the project is now due to finish by 27 November.
It had initially been scheduled to run from 5 to 28 October.
The extension allows the Department to close the road between 8pm and 3am each day, but this will only happen when weather and tidal conditions permit.
The 23-tonne flap gate was craned back into position last weekend, after undergoing maintenance work in Ramsey, and crews now need to dismantle the working area and cofferdam beneath the structure.
Minister sees patient waiting more than 24-hours during visit to ED
Lifeboat assists stricken yacht off Calf of Man
20mph rollout continues as DOI 'refines approach'