Report into Manxman issues expected by March
A capital dredge 'remains under active consideration' by government according to a new document published today (19 November).
The question-and-answer briefing contains information agreed between the Steam Packet Company (SPC), Treasury, the Department of Infrastructure and the Isle of Man Ship Registry.
It confirms that a report into the issues facing Manxman from Lloyd's Register is 'expected by the end of March 2027'.
'Like-for-like' components (new shaft liners) are currently being fitted on the vessel, which has been out of action for several months.
That's despite the Isle of Man Ship Registry recently suggesting the problems may be a design flaw, as the vessel was originally meant to have oil lubricated stern tubes, but this changed to water lubricated bearings early in the project.
You can read more on that HERE.
The 'like-for-like' components 'have been manufactured from a slightly different alloy to original, which has greater surface hardness'.
Additionally, as 'the root cause has not yet been identified', the risk of problems recurring 'cannot be determined' at this time.
DEPTHS
Elsewhere, the new document discusses what the correct depths are in Douglas Harbour for the SPC's vessels to operate.
The Sea Services Agreement (SSA) stipulates that the Department of Infrastructure Harbours division must maintain the navigational approach channel to both linkspans, each with associated manoeuvring area and each of 6-metre depth below Admiralty Chart Datum.
It must also maintain a berth of 5m depth in front of Berth 1 Linkspan (Victoria Pier) and 6.5m depth in front of Berth 5 Linkspan (King Edward VIII Pier).
However, the document states that 'there are certain points that do not comply with the parameters specified in the SSA, particularly beneath the fenders on Berth 5'.
Indeed, 'the Steam Packet has requested that the Department increases Berth 1 to 6.5m for operational resilience and to meet the needs of the future fleet', and an email published earlier this year further reiterated the company's concerns.
Despite this, a capital dredge still has not been ordered.
It instead 'remains under active consideration as part of the long-term development of Douglas Harbour'.
The document states: "Funding is being sought to progress the necessary preparatory work.
"A licensed disposal route is a key prerequisite and work towards establishing that is underway.
"In the meantime, the operational focus remains on monitoring, maintenance dredging, contractor support and continued improvements to harbour dredging capability.
"Capital dredging should be viewed as a strategic investment in long-term resilience and future capacity rather than a substitute for routine maintenance dredging."
You can find the document in full HERE.
Work continues towards under-16 social media ban consultation
Private school records £1.5m loss
Plans to be submitted for new STEM block at QEII High School
'Too soon to say' if Big Manx Feast will return in 2027